Indo MIM

Indo MIM

Metal Injection Molding

Comprehensive SMED Solution for Indo MIM

Global SMED Implementation Across Two Continents

Challenge & Solution

The Challenge

  • Indo MIM needed a comprehensive SMED solution for their facilities in India and USA. Key challenges included: no crane availability in the USA facility preventing vertical loading, space constraints on some molds for standard couplings, strict budget requirements, need for operator self-sufficiency to minimize costs, and integration with existing machine controls.

The Solution

  • SELPLAST engineered a complete SMED ecosystem including mold storage racks, electric and manual moving cars, docking systems, hydraulic clamping, multi-couplings, and full integration with machine HMI. The solution was designed for operator self-installation to save over $80,000 in costs.

Before & After Comparison

Quantified operational improvements

MetricBeforeAfterImprovement
Mold Change Time
>30 minutes
<9 minutes
>70% reduction
Installation Cost
$80,000+
Self-installed
$80,000 saved
Mold Handling
Crane required
Horizontal loading
Crane-free operation

These improvements represent measurable operational enhancements achieved through our solution implementation

Key Results

Measurable improvements achieved through our solutions

<9

Minutes

Target changeover time achieved

1,200

kg

Maximum mold weight handled

$80,000

Saved

Through self-installation

2

Countries

Simultaneous implementation

Implementation Details

  • Mold Storage Racks for organized mold management
  • Fully Electric Moving Cars for automated mold transport
  • Manual Moving Cars as backup and interim solution
  • Docking Rails for precise mold positioning
  • Pre Rollers and Support Blocks retrofitted on machine platens
  • Free Rollers with mold safety and centering features
  • MOD double-acting hydraulic clamping (hydraulically actuated, mechanically locked)
  • Full integration with machine HMI for enhanced safety and automation
  • Ejector Couplers for quick connection
  • Standard 6+6 multi-couplings for water on core side
  • Customized 3+3 multi-couplings for cavity side due to space constraints

Solutions & Products Used

Mold Handling System

Electric and manual moving cars with docking rails

Hydraulic Clamping System

MOD double-acting clamps with mechanical locking

Multi-Coupling System

Customized water/hydraulic quick connections

Integration Package

Machine HMI integration with safety features

Additional Benefits

  • Comprehensive training program in Bangalore facility
  • Customer team fully trained for self-sufficiency
  • Standardized 'Project Playbook' for consistent implementation
  • Solution scalable across 100+ machines and thousands of molds
  • No rework required on existing systems
  • Suitable for greenfield facilities without overhead cranes

Ready to Transform Your Operations?